10.09
2019

ADYR Constructions was awarded a PM Contract

ADYR Constructions was awarded a PM Contract for the Upgrade of Platform no. 21 at the Port of Ashdod, Israel

30.04
2019

ADYR Constructions was awarded a PM Contract

ADYR Constructions was awarded a PM Contract for the Construction of a Grain Conveying System at the Port of Ashdod, Israel

15.04
2019

Milestones 19, 22 & 24 successfuly completed!

Hamifratz Port Project at Haifa, Israel.

A great effort by all parties brought us to successfully complete three major Milestones on time!

  • Milestone 19 & Mile Stone 24 – 400 meter length (out of 800 designed, construction is ongoing) of Quay No’ 6 (-17.3m), a Quay that will bring Hamifratz Port in one line with the worlds Ports, capable to allow mooring of EEE vessels.
  • Milestone 22 – 445 meter length of Quay No’ 7 (-15.5), a Quay that will allow mooring of Post Panamax vessels.

There is no rest for the construction team! We have to look ahead, continue our work and complete the upcoming Milestones and the entire Project according to plan!

What a great achievement! well done guys!

14.01
2019

ADYR Survey team starts the bathymetry Survey at the Port of Eilat, Red Sea Israel.

ADYR Survey team starts the bathymetry Survey at the Port of Eilat, Red Sea Israel.

We are proud to hold capabilities to maneuver our gear from place to place and supply Survey services all over the country!

06.01
2019

Hamifratz Port Project, 2018 achievements

The amount of work done throughout this year is outstanding, here are some Construction figures:

Unit Total Done during 2018 Progress
Antifers No. 43,000 15,113 100%
Reclamation m3 10,140,000 1,483,521 100%
Soil Improvement m3 10,685,402 4,343,165 89%
Fascia Beam m 1,965 1,092 59%
Bored Piles No. 1,274 790 62%
Crown wall m 530 530 100%
Crane Rail m 3,930 1,500 41%

We would like to thank our staff and all Contractors on site for the effort given to achieve those wonderful results!