Finishing of Main Breakwater construction (Haifa Terminal Port Project)
At the 03.11.2018 finally has been completed 882 meters Main Breakwater (Haifa Terminal Port Project).
Started from Juny 2015, it took approximately 2 years to finish all the structure.
Has been placed:
1,100,000 – E type rock (0-1000kg)
290,000 – D type rock (1-3t)
17,440 – C type rock (3-6t)
16,049 – 4 m^3 concrete units
14,551 – 7 m^3 concrete units
1,378 – 12 m^3 concrete units.
We want to say a big thanks to our Contractor “Shaphir-Ashtrom” and to their Sub-contractor “Aras Marine”. Your done a good work and we are proud of our big team.
We sure the Breakwater will do it’s job and people will admit your professionalism!
- Categories:
- news
Recent Posts
- The one of the biggest container ship with a volume of 19,224 TEU will dock in Hadarom Port Terminal
- Shana Tova 5783 – Happy New Year!
- ADYR Constructions is excited to announce the arrival of our new ROV!
- ADYR Constructions was awarded a PM Contract of an new Ammonia Plant
- ADYR Constructions was awarded a PM Contract
Recent Comments
- viagra uk on First Take Over Milestone 2.5 months before the original planning !!!
Archives
Categories
Download Brochures
Contact us now
7100 Athens Place Washington, DC 20512-7100
Hotline: 1 234 567 89