Hadarom Port Terminal

Marine Engineering
Location: Ashdod, Israel
Client: Israel Port Company
Budget: 3.5 Milliard US$
Years: 2014-2022 (On Going Project)
Services: PCMC - Project Construction Management Company
The Project:

Management and coordination for the design and construction of a new container terminal in Ashdod that will include:

  • 3 loading platforms in total length of 2120 meters (1550 meters are for the containers).
  • 600 meters Main breakwater.
  • 1050 meters secondary breakwater.
  • Dredging, filling and compaction of 11.5 million Cube meters.
  • Total area terminal is 300 acres.

Construction of a working port that will be used for the winning contractor to build the new terminal.

Primary Quantities:

Supply and laying 6 million Ton of various size rocks , casting and installing 28,000 "Antifer" concrete cubes in weights 15, 40 and 44 tons each (Total Volume of 300,000 cubic meters concrete), casting 100,000 cubic meters of concrete walls and pavements, 80,000 tons of sheet piling (include accessories and anchors) .

The design has includes:

  • Acquiring the Building Permit, detailed design and preparation of tender documents for the working port.
  • Performing numerical, hydraulic and physical models in laboratories for agitation and stability research.
  • Environmental Impact Study.
  • Geological, Geotechnical and Seismic investigations with a 60 Million NIS budget and 10 months duration.
  • Determining the design criteria and the conceptual design.

The first stage of the design was completed in 09/2011 at a total cost of 100 Million NIS.